SWMS checklist for principal contractors

The principal contractor must obtain a SWMS before high risk construction work starts, and in practice most also review it. This is the checklist we use when reviewing subcontractor SWMS for builders. Subbies can use it to check their own before sending it in.

By iHSEQ Pty Ltd, WHS and ISO consultants · Updated 31 October 2026

Site details, HRCW and scope

  • checkCorrect site address and project name (not another job)
  • checkSubcontractor business name, ABN and contact
  • checkPrincipal contractor named
  • checkPerson responsible for implementing and monitoring the SWMS
  • checkDate prepared and date submitted
  • checkHRCW categories ticked match the work described
  • checkNothing missing, for example falls over 2 metres on a roofing job, or powered mobile plant where an excavator is on site
  • checkScope matches the subcontract and the program

Work sequence and controls

This is where most SWMS fail. You want to see the work in order and controls that a worker could actually follow.

  • checkSteps listed in the order the work is done
  • checkHazards linked to the HRCW, not a generic list
  • checkControls follow the hierarchy: elimination and engineering before admin and PPE
  • checkNo vague wording like "take care" or "be aware"
  • checkSpecific equipment named (scaffold type, EWP, harness system, trench shoring)
  • checkResponsibility assigned for key controls

Isolation, permits and emergency

  • checkIsolation and test-for-dead sequence for electrical, gas or pressurised services
  • checkPermits listed (hot work, confined space, excavation, dig)
  • checkUnderground services located before digging
  • checkRescue plan for falls arrest and confined space work
  • checkFirst aid and emergency contacts consistent with the site plan

People, licences and consultation

  • checkHigh risk work licences listed where needed (boom-type EWP 11 m or more, rigging, scaffolding, crane, forklift)
  • checkAsbestos, electrical or other trade licences listed where relevant
  • checkGeneral construction induction (white card) for all workers
  • checkRecord of consultation with workers
  • checkWorker sign-on sheet

How to send it back without starting a fight

When a SWMS fails review, list the specific gaps rather than writing "not acceptable". For example: "No isolation sequence for the switchboard work", "Falls over 2 metres not ticked but roof work is in scope", or "Site address is for another job". The subcontractor owns the content, so let them fix it.

Agree a turnaround time and do not let the work start until the revised version is in. If a subbie keeps sending generic SWMS, raise it at the pre-start or tender stage, not on the morning they mobilise.

Monitoring after work starts

Obtaining the SWMS is not the end of it. The work has to be done in line with the SWMS. Walk the work area and compare it with the document: is the scaffold, EWP or trench support what the SWMS says? Are the workers on site the ones who signed on? If the method has changed, the SWMS needs to change too.

Review and keeping

Check there is a review date or trigger and a version number. If the method changes on site, the SWMS should be revised and the principal contractor given the updated copy. Keep all versions. If there is a notifiable incident, keep the SWMS for at least 2 years.

Common questions

Does the principal contractor have to approve a SWMS?

The law requires the principal contractor to obtain the SWMS before HRCW starts and to put arrangements in place so the work follows it. Most builders review it as part of that, but responsibility for the content stays with the subcontractor.

What should I do if a subcontractor SWMS is generic?

Send it back with the specific gaps listed. A generic SWMS must be reviewed and changed for the actual site before it is used.

How often should a SWMS be reviewed on site?

Whenever controls change, when the work is not being done as written, and after an incident. Many sites also set a review at fixed intervals.

Sources

General information only, current at the date above. Legislation changes — confirm requirements with your state regulator. As the PCBU you remain responsible for your SWMS.