Who prepares, signs and keeps a SWMS?

On site, nobody argues that a SWMS is needed. The arguments are about whose job it is: the subbie, the builder, the supervisor or the workers. The WHS Regulations are clear on most of it, and some of what sites insist on, like signature sheets, comes from good practice and contract terms rather than the law itself.

By iHSEQ Pty Ltd, WHS and ISO consultants · Updated 31 October 2026

The PCBU doing the work prepares it

Under r 299 of the model WHS Regulations, a person conducting a business or undertaking (PCBU) that carries out high risk construction work must ensure a SWMS is prepared before the work starts, or that one has already been prepared by someone else. In practice that is the business doing the high risk work, usually the subcontractor, not the builder.

The PCBU can have a consultant, a template or a generator do the drafting, but the duty does not move. The PCBU has to make sure the SWMS identifies the high risk work, the hazards and risks, the control measures and how those controls will be implemented, monitored and reviewed. It must also take into account the site conditions and the principal contractor's WHS management plan, and be easy for workers to find and understand.

Victoria uses the OHS Act 2004 and OHS Regulations 2017. The SWMS duty sits with employers and self-employed persons rather than PCBUs, but the practical answer is the same: the business doing the work prepares it.

Consulting the workers

Safe Work Australia's guidance says the SWMS should be prepared in consultation with the workers who will do the work, and with any health and safety representative. If the crew has not been engaged yet, consult them when the SWMS is first rolled out, for example at induction or a toolbox talk. Reviews should also be done with the affected workers, including subcontractors.

Consultation is a real conversation, not a signature. Ask the people who do the task what goes wrong, what equipment they actually use and whether the steps match how the job is done.

Do workers have to sign a SWMS?

The regulations do not require signatures on a SWMS. Safe Work Australia's template says a SWMS may include the names of workers consulted, the date and their signatures, and WorkSafe ACT describes this as optional. Signatures are a way to record consultation and that workers have read the SWMS.

That said, nearly every principal contractor requires a worker sign-on sheet, and it is good evidence that the SWMS was communicated. A signature is not proof of understanding, so the supervisor should still walk the crew through it. Workers who arrive part way through the job need to be briefed and signed on before they start.

What the principal contractor must do

On a construction project, the principal contractor has extra duties. Under r 312 it must take all reasonable steps to obtain a SWMS from each contractor before high risk construction work starts. Under r 301 the contractor must give the principal contractor a copy before starting. The WHS management plan must set out how SWMS are collected, assessed, monitored and reviewed. A construction project is generally work costing $250,000 or more, though the trigger differs in some jurisdictions (the NT uses $500,000).

The principal contractor does not "approve" a SWMS in a legal sense. It obtains it, reviews it as part of its own arrangements and monitors that work follows it. Responsibility for the content stays with the PCBU doing the work.

The supervisor on site

Regulation 300 requires the PCBU to put arrangements in place so the high risk work is carried out in accordance with the SWMS. That usually falls to the leading hand or supervisor. Their job is to:

  • checkBrief every worker on the SWMS before they start, and run the sign-on
  • checkCheck the equipment and controls on site match the SWMS
  • checkStop the work if it is not being done as written
  • checkRaise changes so the SWMS can be reviewed and reissued
  • checkKeep the current version on site or quickly available, paper or electronic

Stop work and review triggers

If high risk work is not being done in accordance with the SWMS, it must stop immediately or as soon as it is safe to do so, and must not resume until it can be done in line with the SWMS. If the crew has found a better or safer method, update the SWMS before restarting rather than just carrying on.

Under r 302 the SWMS must be reviewed and, as necessary, revised when the relevant control measures change. Common triggers are a change in method, equipment, site conditions or crew, an incident or near miss, a worker or HSR raising a concern, and a builder's audit finding. After a revision, tell everyone involved, give the principal contractor the new copy and brief the affected workers.

How long to keep a SWMS

Keep the SWMS available for inspection until the high risk construction work is finished, and keep all versions if it is revised. If a notifiable incident happens during the work, keep the SWMS for at least 2 years from the date of the incident. It can be stored at the workplace or somewhere it can be delivered promptly, including electronically. Many businesses keep SWMS for longer as part of their records system, which costs little and helps if a claim or investigation comes later.

Common questions

Who is responsible for writing a SWMS?

The PCBU carrying out the high risk construction work, usually the subcontractor. They can get help drafting it, but they must make sure it is prepared before work starts and reflects the site.

Do workers legally have to sign a SWMS?

No signature is required by the regulations. Signatures are an optional way to record consultation, but most principal contractors require a sign-on sheet as a site rule.

Does the builder have to approve my SWMS?

No. The principal contractor must take reasonable steps to obtain it before high risk work starts and monitor that work follows it. The content remains the subcontractor's responsibility.

How long do you have to keep a SWMS?

Until the high risk work is finished, including every revised version. If there is a notifiable incident, keep it for at least 2 years from the date of the incident.

Sources

General information only, current at the date above. Legislation changes — confirm requirements with your state regulator. As the PCBU you remain responsible for your SWMS.

See a finished SWMS first

A complete 14-page example as a Word document, emailed to you.

We'll email the sample once and may follow up to see if you need a hand. No spam, unsubscribe any time. Privacy