SWMS for elevating work platforms (EWPs)

Scissor lifts and boom lifts are on almost every commercial job, and most of the serious EWP incidents we see come from the same few causes: tip-overs, crush against overhead structures, contact with powerlines and falls from the basket. Safe Work Australia says construction work using an EWP is likely to be high risk construction work, so in most cases you need a SWMS before the machine goes up.

By iHSEQ Pty Ltd, WHS and ISO consultants · Updated 31 October 2026

Scissor lifts vs boom lifts

Safe Work Australia lists the common EWP types as scissor lifts, self-propelled boom lifts, trailer lifts, truck or vehicle-mounted lifts, telehandlers with EWP attachments and vertical mast lifts. For SWMS purposes the big split is between scissors and booms.

  • checkScissor lift: the platform goes straight up. The main risks are tip-over on poor or sloping ground, crush against the ceiling or slab soffit, and falling objects. A harness is only needed if a risk assessment says so.
  • checkBoom lift: the basket can extend out and over. Add catapult and free-fall risk from the basket. Safe Work Australia says a full harness must be worn and attached to the designated anchor point, with a short lanyard and energy absorber.

Licences and training

A high risk work licence (class WP) is required to operate a boom-type EWP with a boom length of 11 metres or more. The boom length is measured from the original design, so a machine that has been modified to a shorter boom still needs the licence. You must see the licence or written evidence before letting someone operate it. Telehandlers with a boom over 11 metres also need a licence.

Below 11 metres, and for scissor lifts, no licence is required, but operators still need training, information and instruction. In practice that means a recognised EWP operator course plus a familiarisation on the specific make and model, including the ground controls.

When an EWP job is high risk construction work

An EWP does not appear by name in the 18 HRCW categories, but EWP work usually triggers one or more of them:

  • checkRisk of a person falling more than 2 metres, from the basket or during access
  • checkWork on or near energised electrical installations, including overhead powerlines
  • checkWork in an area with movement of powered mobile plant, which the EWP itself and nearby plant create
  • checkWork on or next to a road or other traffic corridor in use by traffic
  • checkWork near a shaft or trench deeper than 1.5 metres, where outriggers or wheels are close to the edge

Key controls to write into the SWMS

Generic statements like "operate EWP safely" will not get through a builder's review. Write down what you will actually do:

  • checkPre-start check against the manufacturer checklist and logbook: alarms, emergency lowering, interlocks, tyres, outriggers, gates and service status. If it fails, tag it out.
  • checkGround conditions checked for bearing capacity, slope, soft fill, recently backfilled trenches, pits and underground services
  • checkMachine used within its slope rating and wind limit from the data plate, with the sail effect of sheet materials considered
  • checkHarness and short lanyard attached to the basket anchor point on boom lifts at all times
  • checkCrush controls: plan the travel path, keep clear of overhead structures, use secondary guarding where available
  • checkExclusion zone with barricades below the basket and around the machine, and no loads over footpaths or roads
  • checkSpotter or traffic management where other plant, vehicles or pedestrians are close
  • checkOperator holds a WP licence where the boom is 11 m or more

Rescue plan

Every EWP SWMS needs a rescue plan that works on this site. Who on the ground knows how to use the base controls and emergency lowering? Are the ground controls reachable, and is the lowering path clear? What happens if the machine fails at height or an operator is suspended in a harness? Safe Work Australia's guide says rescue should start immediately after a fall into a harness, because suspension intolerance can set in quickly, and that people using harnesses should not work alone. Practise it before you need it.

Overhead powerlines

Approach distances to overhead powerlines are set by state and territory electrical safety laws and codes, and they vary with voltage and the training of the people involved. Do not copy a distance from another state's SWMS. Check your local electricity regulator or network operator and write the actual distance for this site into the SWMS.

Safe Work Australia's guide requires a trained safety observer (spotter) with stop authority where the EWP could encroach on the approach distance while moving. Where work inside the no-go zone is unavoidable, it needs the network operator's approval and possibly a permit or de-energisation. In Victoria, Energy Safe Victoria's No Go Zone framework sets a 3.0 to 6.4 metre spotter zone for distribution lines, with network operator permission needed inside 3 metres.

If the machine contacts a line, occupants should stay in the basket until a competent person says it is safe. The EWP must be taken out of service until it is inspected.

Common questions

Do I need a licence to operate a scissor lift?

No high risk work licence is needed for a scissor lift, but the operator must be trained and familiar with that machine. A WP licence is only required for boom-type EWPs with a boom of 11 metres or more.

Do you need a harness in a scissor lift?

Not automatically. Safe Work Australia says harnesses are required in boom-type EWPs, and in other EWPs only where a risk assessment shows they are needed. Many principal contractors set their own site rules.

Is using an EWP high risk construction work?

Usually. Safe Work Australia says construction work using an EWP is likely to be HRCW, most often because of the risk of falling more than 2 metres, powerlines, mobile plant or traffic.

What is the safe distance from powerlines for an EWP?

It depends on the voltage and your state or territory. Check your electricity regulator or network operator. In Victoria, a spotter is needed between 3.0 and 6.4 metres from distribution lines.

Sources

General information only, current at the date above. Legislation changes — confirm requirements with your state regulator. As the PCBU you remain responsible for your SWMS.

See a finished SWMS first

A complete 14-page example as a Word document, emailed to you.

We'll email the sample once and may follow up to see if you need a hand. No spam, unsubscribe any time. Privacy