What is a SWMS?

A SWMS (Safe Work Method Statement) is a short document that sets out high risk construction work, the hazards it creates and how those hazards will be controlled on a particular job. It is a legal requirement before high risk construction work starts. If you are a tradie working for a builder, it is usually the first document they ask for.

By iHSEQ Pty Ltd, WHS and ISO consultants · Updated 31 October 2026

A SWMS in one sentence

A SWMS is the plan for doing a high risk task safely on this site, written so the workers doing it can read it and follow it.

It is not a policy manual and it is not a risk register. Safe Work Australia's guidance says it should be short, in plain language, and focused on the high risk construction work. Pictures and diagrams are fine. Long lists of risk scores and references to standards are not what an inspector wants to see.

When is a SWMS required?

Under the model WHS Regulations, a SWMS must be prepared before any high risk construction work (HRCW) starts. HRCW is defined in regulation 291 as 18 types of work. The common ones on a building site are:

  • checkWork where a person could fall more than 2 metres
  • checkWork on or near energised electrical installations or services
  • checkTrenches or shafts deeper than 1.5 metres, and tunnels
  • checkWork likely to disturb asbestos
  • checkDemolition of load-bearing structures
  • checkWork in areas with movement of powered mobile plant
  • checkWork on or next to roads or railways used by traffic
  • checkWork in or near a confined space

Who prepares it?

The PCBU (person conducting a business or undertaking) carrying out the high risk work prepares the SWMS. On a building site that is normally the subcontractor doing the task, not the builder.

It must be prepared in consultation with the workers who will do the work and any health and safety representatives. A SWMS written in an office and never shown to the crew does not meet that duty.

On a construction project, the principal contractor must obtain the SWMS before the high risk work starts. Under the model laws a construction project is one where the construction work costs $250,000 or more (r 292). The Northern Territory uses $500,000, and Victoria applies its principal contractor duties to construction projects of $350,000 or more under the OHS Regulations 2017.

What a SWMS must contain

At minimum, a SWMS must:

  • checkIdentify the high risk construction work
  • checkState the hazards and risks to health and safety from that work
  • checkDescribe the control measures
  • checkDescribe how the controls will be put in place, monitored and reviewed

Keeping and reviewing it

The SWMS has to be kept on site, or somewhere it can be delivered quickly, until the high risk work is finished. Electronic copies are fine. If it is revised, keep every version. If a notifiable incident happens, keep it for at least 2 years from the incident.

Review it whenever the control measures change. If the work is not being done the way the SWMS says, stop the work as soon as it is safe, review the SWMS, and do not restart until the work can follow it (s 300 requires arrangements to make sure the work is done in line with the SWMS).

What happens if you do not have one?

Inspectors can issue improvement or prohibition notices and, in many states, on-the-spot fines. Prosecutions are possible and penalties for corporations are significant. The more practical problem is that most builders will not let you start without one, and a generic SWMS is often sent back.

Common questions

Is a SWMS a legal requirement?

Yes, for high risk construction work. The PCBU doing the work must prepare it before the work starts and make sure the work is done in line with it.

Do I need a SWMS for small jobs?

If the job includes high risk construction work, yes. The size of the job does not matter. Work of a minor nature may not be construction work at all, so check the regulator guidance for your state.

How long is a SWMS valid for?

There is no fixed expiry. It applies until the high risk work is finished, and must be reviewed whenever controls change or the work is not being done as written.

What does SWMS stand for?

Safe Work Method Statement.

Sources

General information only, current at the date above. Legislation changes — confirm requirements with your state regulator. As the PCBU you remain responsible for your SWMS.

See a finished SWMS first

A complete 14-page example as a Word document, emailed to you.

We'll email the sample once and may follow up to see if you need a hand. No spam, unsubscribe any time. Privacy